Project Ref: | 41798 |
Client: | LBBJV |
Project: | Crane for the Airportlink Project in Brisbane |
Scope: | 260t double girder overhead crane |
In 2006 LBBJV purchased all the cranes for the TBM (Tunnel Boring Machine) launch site at Bowen Hills for the Chlem 7 tunnel construction. Among those cranes was a fully customised 260t overhead crane, this crane was 100% designed and manufactured in Australia at Eilbeck Cranes Ingleburn NSW plant.
The crane was taken from concept design and delivered to site in 14 weeks from placement of order. A delivery schedule which is something that Eilbeck Cranes has a well-earned reputation for.
Airportlink is Brisbane’s new 6.7 km toll road, connecting the CBD to Brisbane Airport, Australia TradeCoast and the rapidly growing northern suburbs.
It is Australia’s largest privately funded transport infrastructure project to date, and is on track to open to the public mid-2012. Primarily underground, Airportlink connects the Clem7 Tunnel, Inner City Bypass and local road network at Bowen Hills, to the northern arterials of Gympie Road, Stafford Road at Kedron, Sandgate Road, and the East West Arterial leading to the airport and Australia TradeCoast.
When complete, Airportlink will play a key role in building a better Brisbane community by enhancing choice, reducing congestion and transforming the road network.
Airportlink is a multi-destination road, servicing an area that contains more than 60% of the Brisbane population. It will boost business efficiency in the economic heart of one of Australia’s highest growth cities.
BrisConnections has contracted Thiess John Holland, a joint venture between Thiess Pty Ltd and John Holland Group, to undertake the design and construction of Airport Link, Northern Busway (Windsor to Kedron) and Airport Roundabout Upgrade. A separate Thiess John Holland entity will provide operations and maintenance services to BrisConnections for the first five years of operations.
Airport Link, Northern Busway (Windsor to Kedron) and the Airport Roundabout Upgrade are expected to be completed by mid 2012.
FMG Iron Bridge Contract for 20 conveyor winches
The latest ES80 50 t Mucking Crane packed with heaps of safety features
New addition to the Eilbeck ES Hoist range 10 t x 70 m HOL with man riding features with dual…
Designed in Sydney by Eilbeck's Engineering Team, the 500t full portal crane, and the additional…
Eilbeck has been engaged in pre tender of the design of segment handling cranes for the precast…
100t and 2 off 50t Tunnelling Site Overhead Cranes for John Holland & KBR JV
The 100t full portal crane commissioned at the East Site primary crusher facility has passed the…
The new 25t x 17m span double girder overhead crane, manufactured in Eilbeck’s state of the art…
Eilbeck worked closely with BHP to develop the best crane solution for shell demolition, shell…
The higher class was a requirement due to the intended heavy use of these cranes, as Steel Force are…
We see the requirement of Eilbeck to manufacture in Australia to keep quality guaranteed high, and…
The crane capacities are huge, the main winch lifting 100t for heavy machinery retrieval from a 100m…
Eilbeck supplies 5t x 52.5m span EDL crane to Sikorsky Airport Base at Yerriyong
When global oilfield provider of engineered services and products to the offshore oil and gas…
As part of Rio Tinto Iron Ore’s Rail Capacity Enhancement project, Eilbeck Cranes has supplied three…
120t x 10m FPZLK
Eilbeck Cranes has successfully completed Factory Acceptance Testing and delivered 5 cranes capacity…
260t x 23.39m ZLK Crane, Airport Link Project - Brisbane
Australian Overhead Crane Engineering at the Height of its Game
10t Circular Crane
Veolia MBT Crane
Eilbeck cranes for NorthConnex
7 Mile Upgrade RSM
Overhead Cranes for Jandakot Project
InfoSitemapDisclaimer |
NewsCareersNewsletters |
MediaProjectsBrochures |
ContactContact UsOnline Quotes |