Temporary Construction Cranes for the Electric Slag Furnace Rebuild at Olympic Dam (SA)


When client BHP Billiton wanted to utilise temporary special construction cranes for their Electric Slag Furnace Rebuild (ESFR) at Olympic Dam Mine Site (SA), they turned to Eilbeck Cranes and both worked closely together to bring to light a bespoke engineered solution for this special application.

Lifting hoists travel synchronously while maintaining 5 + 5T (2 off 5T) MRC and independently maintaining 5t MRC each.

The temporary construction cranes were planned to be used for the ESFR Major Shutdown (MSD) at the Olympic Dam facility.

The requirement was for the temporary construction cranes to be specifically designed ‘fit-for-purpose’, fabricated, tested and commissioned to meet the construction requirements of the ESFR strict standards whilst complying with Australian and key BHP Billiton Standards.

The Scope comprised the supply of several crane, of which two were specifically designed and built for the ESFR:

  • ESFR-01: Transfer Crane – 10t
  • ESFR-02: Circular Crane – 10(5+5)t


The hoists travel together circumferentially (long travel of the crane) and travel both independently and synchronised in the radial direction in full 360° (cross travel). The hoists are able to lift independently and synchronised.

The centre line diameter of circular monorail is 11.08m, and it had to be divided into sections for ease of handling and installation on site. The assembly and erection plan of the circular monorail had to be engineered in a very specific way in order to be executed safely and efficiently on site.

read the full article



Eilbeck Newsletters

WA Premier Visit

Posted on: May 13, 2020

WA Premier Mark McGowan and Transport Minister Rita Saffioti visited Eilbeck Crane Bassendean

FK Gardner - IMS Mackay Building

Posted on: Aug 5, 2019

Through building head contractor F K Garner and Sons, a builder which Eilbeck Cranes has worked extensively before with…

Melbourne Metro Tunnel Segment Yard Cranes

Posted on: May 13, 2019

Eilbeck Cranes has delivered cranes for the Precast yard in Deer Park – Segment Factory Ravenhall, Victoria. This…

Loco Crane Replacements

Posted on: Mar 13, 2019

Eilbeck has been commissioned to manufacture and deliver 2 double girder cranes 75/20 tonnes each, to replace the old,…

Sydney Metro 2 – All Cranes Delivered

Posted on: Oct 11, 2018

A total of 18 cranes has been manufactured to cater the needs of the project’s tunneling and segment yard sites.

Sydney Metro 2 – Load testing and Complete Assembly

Posted on: Aug 13, 2018

On Tuesday 7th of August Eilbeck Cranes achieved another milestone in the delivery and commissioning of the Sydney Metro…

Sydney Metro 2 – Ahead of schedule

Posted on: Jul 16, 2018

Last Wednesday Eilbeck Cranes delivered and installed another crane for the biggest public transport project in…

YouTube   Facebook   Linkedin   View profile on ICN Gateway

Sydney
6 Moorlands Road
Ingleburn NSW 2565


Newcastle
1/50 Sandringham Avenue
Thornton NSW 2322


Brisbane
3/12 Sudbury Street
Darra QLD 4076


Mackay
32 Diesel Drive
Paget QLD 4740


Perth
28 Jackson Street
Bassendean WA 6054


Adelaide
2/23 Clovelly Avenue
Royal Park SA 5014


Melbourne
321 Doherty’s Road
Truganina VIC 3029